Lansing City Council hears updates on street improvement and bridge projects, initiates request for engineering qualifications

by Joshua Sharpe

The Lansing City Council met in regular session Monday, September 15. The hour-long meeting included approval of such matters as a pay estimate for an ongoing street project, an LP gas bid, sewer bill forgiveness, a request for engineering qualifications, and an audit agreement. Discussion also took place regarding a retaining wall concern previously presented, marina improvements, updates on the ongoing bridge project, and open meetings certification.

STREET PROJECT PAY ESTIMATE
The council approved a partial payment estimate in the amount of $176,063.55 to Skyline Construction for the North, Platt and Fourth Streets improvement project. Lansing Mayor Mike Verdon offered a brief project update from the bi-weekly project meeting recently held, noting that the project is “about 44% complete” as of the September 15 meeting.

SEWER BILL ADJUSTMENT
Approval was also granted by the council for a partial sewer bill forgiveness consistent with past practice for non-negligent leaks. PeopleService representative Duane Estebo explained the water leak of approximately 100 gallons that resulted in the larger sewer bill came from a supply line to the residence on the property and was not due to any faulty hose or other negligence on the part of the property owner.

LP BID
The council compared seasonal LP pricing and equipment terms when considering bids for the 2025-2026 heating season. Mayor Verdon read the bids aloud, which included a quote of $1.23 per gallon from Consolidated Energy, and another from AgVantage FS in the amount of $1.18 per gallon. Consideration of tanks and other equipment was also involved in the discussion, with the council approving the low bid of $1.18 per gallon from AgVantage FS.

REQUEST FOR QUALIFICATIONS
The council initiated a request for qualifications for engineering services to align with Iowa Department of Transportation (DOT) work and covering an area outside the DOT project scope in regard to the proposed State Highway 9/Main Street improvements project. Mayor Verdon framed the process and scope, noting that the city is requesting qualifications from engineers to prepare the preliminary engineering report and final plans and specifications, along with construction inspection, and engineering services for a water/sewer project to be completed in conjunction with the overall DOT project for an adjacent one-block section of Main Street from Second Street to Front Street that would not be part of the DOT’s portion of the project.

To read the full article, pick up the Wednesday, September 24, 2025 print edition of The Standard or subscribe to our e-edition or print edition by clicking here.